| Objective(s) |
i. To import additional 500 MW power from India through capacity upgradation of the existing Bangladesh (Bheramara) – India (Baharampur) Grid Interconnection. ii. To meet up the ever increasing demand of electricity for socio economic development in both the countries. |
| Scope of Work |
1. 230 kV Double Circuit Transmission Line with river crossing : 12 km (Double Circuit Tower, Quad Mallard) 2. 500 MW HVDC Back-to-Back Station (2nd Module) including 400 kV & 230 kV Switchyard Equipment, Control & Protection etc. 3. 230 kV Bay extension: 4 nos. |
| Project Cost | Total: 185479.51 Lakh BDT; GoB: 58091.26 Lakh BDT; Project Aid: 100045.23 Lakh BDT; PGCB: 27343.02 Lakh BDT |
| Development Partner | ADB |
| Duration | January, 2015 to December,2018 |