| Objective(s) |
i. Promote Renewable Energy growth (Merchant Plant) to meet the growing energy demand. ii. Optimal utilization of the existing land of the Power Grid for generating green power and creating a new source of revenue. iii. Mitigate greenhouse gas emissions by replacing fossil fuel-based power generation with clean solar power. iv. Diversify the energy portfolio to reduce dependency on imported fuels and enhance energy self-sufficiency. v. Leverage existing grid substations to efficiently integrate solar power into the national grid, reducing transmission losses. vi. Foster economic growth while ensuring environmental sustainability and compliance with global climate commitments, such as the Paris Agreement. |
| Scope of Work | 50 MW Solar Plants across 14 substations. |
| Project Cost | Total Cost: 61988.85 Lakh BDT (PA- 51 mUSD) |
| Development Partner | N/A |
| Present Status | PDPP has been sent to Power Division on 15/01/2025. |
| Estimated Duration | 01/01/2026 to 31/12/2028 |
| Project Office |