| Objective(s) | • To transmit power from upcoming United 583MW as well as United 300MW power plants at Anowara to the major load centers of Chittagong City and Also to strengthen power transmission system in Chattogram area along with enhancing its reliability and efficiency. |
| Scope of Work | a) 400kV Transmission Line: 25.185km b) 230kV Transmission Line: 24.45 km c) 230kV substation: 2 nos d) 230kV bay extension: 4 nos |
| Project Cost | Total:186128.91 Lakh BDT GOB:47229.12 Lakh BDT PA :123531.64 Lakh BDT PGCB:15368.15 Lakh BDT |
| Development Partner | AIIB. |
| Present Status | Physical : 80.18 % Financial : 80.11 % |
| Estimated Duration | July, 2019 to June, 2027 |
| Project Office | Project Director : Bijoy Kumar Das Project Office : Power Grid Head Office Building, Aftabnagar, Dhaka-1212. Mobile : 01711688277 Email : espnca19@gmail.com |