Integrated Capacity Development Project in the Power Transmission System of Bangladesh
|
Objective(s)
|
• Enhancing the knowledge and technical skills of university undergraduate students of Bangladesh on advanced technologies relevant to the power sector and improving the skills of PGCB engineers to achieve power sector targets set by the government.
|
|
Scope of Work
|
Enhancing the knowledge and technical skills of university undergraduate students of Bangladesh on advanced technologies relevant to the power sector and improving skills of PGCB engineers to achieve power sector targets set by the government.
|
|
Project Cost
|
Total: 816.69 Lakh BDT PA : 547.05 Lakh BDT PGCB: 269.64 Lakh BDT
|
|
Development Partner
|
ADB
|
|
Duration
|
July, 2019 to Dec, 2024
|
Last updated on: 2025-07-02 10:26:23
Information Source: Project Planning