Objective(s) • To create power evacuation facilities for upcoming power plants at Mongla (1st unit 660 MW)
• To supply construction power to Mongla power plant
Scope of Work a) 24 km four circuit 230 kV Mongla-Khulna (South) line (Initially two circuit stringing).
b) Two 230 kV bay extension at Khulna (South).
Project Cost Total: 13977.64 Lakh BDT, Local Currency (LC): 7241.06 Lakh BDT, Foreign Currency (FC): 6736.58 Lakh BDT
Development Partner PGCB
Duration Jan, 2015 to December, 2021

Last updated on: 2022-06-05 10:48:53
Information Source: Project Planning