Aminbazar-Savar 132 kV Transmission Line & Savar 132/33 kV Substation Project
|
Objective(s)
|
.
|
|
Scope of Work
|
a) 132 KV Line (15.7 km) from Aminbazar to Savar.
b) New 132/33 KV Substation (150 MVA) at Savar.
|
|
Project Cost
|
Total: 94.55 crore BDT
|
|
Development Partner
|
N/A
|
|
Duration
|
2007-08 to 2009-10
|
Last updated on: 2020-12-30 04:16:50
Information Source: Project Planning