Objective(s) 1. To reduce the fluctuation of the system frequency by providing fast acting spinning reserves for primary frequency control to improve overall system security, stability and resiliency.
2. To mitigate fluctuations of variable renewable energy (VRE) generation and ensure seamless integration of VRE into the national grid.
3. To provide Black Start facility for ensuring fast restoration of the system
Scope of Work 1. 120 MW / 60 MWh BESS at Ishwardi 230/132/33 kV substation
2. 40 MW / 20 MWh BESS at Bhulta 400/230/132 kV substation
Project Cost Total Cost: 110150 Lakh BDT (PA= 54.60 mUSD)
Development Partner ADB
Present Status Feasibility Study ongoing
Estimated Duration 01/10/2025 to 30/09/2027
Project Office

Last updated on: 2025-07-02 10:15:29
Information Source: Project Planning