Objective(s) To evacuate the power to be generated at the proposed power plant at Shahbajpur, Bhola.
To minimize the overloading of the existing Bhola-Patuakhali 33 kV line
To strengthen the power evacuation arrangement & increasing power supply stability, reliability & transmission capability in Barisal area.
Scope of Work 1. Construction of overland 230 kV Transmission Line from Kutuba (Borhanuddin) to Gajalia, Babuganj (Barisal)-55.55 km.
2. Tetulia and Kalbadar River Crossing-5.45 km.
3. 230/132 kV, 3x225 MVA substation at Gajalia, Babuganj.
Project Cost Total: BDT 453.4260 crore(PGCB), Local Currency (LC): BDT 286.4081 crore; Foreign Currency (FC): BDT 167.0179 crore
Development Partner N/A
Duration March, 2011 to June, 2017