Matarbari Ultra Super Critical Coal-Fired Power Project (II) (PGCB Part: “Matarbari-Madunaghat 400 kV Transmission Line”)
|
Objective(s)
|
To create facilities to evacuate power from upcoming Matarbari 1200 MW Power Station and to create power transmission capacity/ facility between Matarbari and Madunaghat.
|
|
Scope of Work
|
To construct 400kV transmission line-94.6 km.
|
|
Project Cost
|
Total: 132304.00 Lakh BDT,GoB: 30906.00 Lakh BDT,Project Aid: 94858.00 Lakh BDT,PGCB: 6540.00 Lakh BDT
|
|
Development Partner
|
JICA
|
|
Duration
|
July, 2017 to June, 2022
|
Last updated on: 2022-07-03 11:11:25