Objective(s) • To address some fundamental measures that must be put in place so that the power system can be operated in a secure and economic manner in line with the longer term goals to deliver much greater quantum of power.
Scope of Work a) Reconductoring of Barisal(N)-Barisal 132 kV Double Circuit line: 10km
b) Reconductoring of Saidpur-Purbasadipur 132 kV Double Circuit line: 30 km
c) Introduction of DLR (Dynamic Line Rating) for 400 km of most important transmission lines of PGCB.
d) Integration of generators to the NLDC’s SCADA/EMS system, upgradation/modernization of the NLDC’s SCADA/EMS system to meet future needs.
Project Cost Total: 30211.70 Lakh BDT, GOB: 5163.43 Lakh BDT, PA: 21868.98 Lakh BDT, PGCB: 3179.29 Lakh BDT
Development Partner World Bank
Duration July, 2017 to June, 2025

Last updated on: 2025-07-02 10:28:46
Information Source: Project Planning